M

L3: Metro Plaza

Project Performance Details

Metro Plaza

At Risk
Allied REITPM: Lisa Wangconcrete
Oct 1, 2024
38% CompleteDay 436 of 242
May 31, 2025-5d
Expected
Completion
38%
+0% this week
Budget Used
0%
$0 under
Schedule
-5d
Behind schedule
Health Score
100
Healthy

CPI

0.97
Target: ≥ 1.00
-$3,000

SPI

0.96
Target: ≥ 1.00
-5d

Margin

13.3%
Target: ≥ 15%
-1.7%

Completion

38%
0%50%100%

Original Budget

$100,000

Revised Budget

$100,000

No changes

Actual Cost

$50,000

50.0% of budget

EAC

$97,000

Estimate at Completion

Variance

$3,000

Under budget

Budget Utilization

55.0%
Actual: $50,000Committed: $5,000Remaining: $45,00090% Warning

ETC

$42,000

Estimate to Complete

Committed (POs)

$5,000

Open Purchase Orders

Approved COs

$0

Change Order Value

Remaining

$45,000

Budget Remaining

CategoryBudgetActualCommittedEACStatus
Labour
$50,000$25,000$48,000
Materials
$35,000$18,000$4,000$34,000
Equipment
$15,000$8,000$2,000$14,500
Subcontract
$8,000$4,000$1,000$7,500
Overhead
$4,000$2,000$3,800
Total$112,000$57,000$7,000$107,800

Cost Distribution

Labour44.5%
Materials31.5%
Equipment13.5%
Subcontract7.0%
Overhead3.5%
Crew/WorkerRoleReg HrsOT HrsAvg RateTotal
Total00$NaN$0
Regular Hours

0

OT Hours

0(NaN%)

Avg Rate

$NaN

Total Cost

$0

Weekly Labor Trend

Week 1Current

Materials

Total: $19,100
ItemVendorQtyUnit $TotalStatus
Heritage Red Brick

PO-2025-0045

Heritage Brick Supply2,500$2.85$7,125Shipped
Type S Mortar

PO-2025-0048

Masonry Supplies Inc50$18.50$925Delivered
Limestone Blocks

PO-2025-0052

StoneWorks Ltd800$8.50$6,800Ordered
Sealant

PO-2025-0055

BuildCo50$85.00$4,250Delivered

Equipment

Total: $14,065
ItemVendorDurationRateTotalStatus
Scaffolding SystemRentAll Construction91 days$115/d$10,465Active
Crane (Daily)HeavyLift Ontario8 days$450/d$3,600Active

Materials Total

$19,100

4 items

Equipment Total

$14,065

2 rentals

Current (0-30d)

$32,000

30-60 Days

$43,700

60-90 Days

$0

Over 90 Days

$0

Total AR

$75,700

Construction Lien Deadline Approaching

12 days remaining

Ontario Construction Act requires liens to be registered within 45 days of last supply. $43,700 at risk.

Invoice #VendorDescriptionAmountDue DateAgeStatus
INV-2025-0198

Dec 15, 2024

RentAll ConstructionScaffolding rental - December$3,450Jan 14, 202551dOverdue
INV-2025-0245

Jan 15, 2025

Masonry Supplies IncType S Mortar and supplies$2,450Feb 14, 202520dPending
INV-2025-0278

Jan 22, 2025

HeavyLift OntarioCrane rental - January$3,600Feb 21, 202513dPending
INV-2025-0267

Jan 20, 2025

StoneWorks LtdLimestone blocks delivery$6,800Feb 19, 202515dDisputed
INV-2025-0234

Jan 5, 2025

Heritage Brick SupplyHeritage red brick - Phase 1$7,125Feb 4, 202530dPaid
Totals$23,425
Paid

$7,125

1 invoices

Pending

$6,050

2 invoices

Overdue

$3,450

1 invoices

Disputed

$6,800

1 invoices

AR Aging Distribution

Current42%
30-60d58%
60-90d0%
90d+0%

Progress

69%

Completed

2

milestones

On Track

1

milestones

At Risk

0

milestones

Delayed

1

milestones

Critical Path

4

milestones

Critical Path Impact: 1 milestone(s) at risk or delayed

Pointing & Finishing - may impact project completion date.

Project Timeline

Oct 1, 2024May 31, 2025
Phase 1: Preparation
Site Assessment CompleteCritical+1d ahead
Nov 1, 2024100%Nov 14, 2024
Scaffolding InstallationCritical+2d ahead
Nov 15, 2024100%Nov 28, 2024
Phase 3: Restoration
Brick Restoration - North WallCritical5d behind
Dec 23, 202475%Jan 20, 2025
Phase 4: Finishing
Pointing & FinishingCritical5d behind
Jan 25, 20250%Feb 20, 2025
MilestonePlanned EndForecastVarianceProgressStatus
Site Assessment Complete

John Smith

Nov 15, 2024Nov 14, 2024+1d
100%
Completed
Scaffolding Installation

Mike Chen

Nov 30, 2024Nov 28, 2024+2d
100%
Completed
Brick Restoration - North Wall

Crew A

Jan 15, 2025Jan 20, 2025-5d
75%
On Track
Pointing & Finishing

Crew A

Feb 15, 2025Feb 20, 2025-5d
0%
Delayed
Pending

2

$18,000

Approved

2

$27,000

Rejected

0

$0

Net Impact

+$50,500

Schedule

+13d

impact to schedule

Oldest Pending

8d

awaiting approval

CO #DescriptionValueScheduleRequested ByDaysStatus
CO-004
Additional scaffolding - south wing

Extended scaffolding rental for south wing access

+$4,2000d
Mike Chen

Jan 15, 2025

20dPending
CO-003
Premium mortar upgrade

Upgrade to heritage-grade lime mortar per architect recommendation

+$8,5000d
John Smith

Jan 10, 2025

25dPending
CO-005
Scope reduction - decorative elements

Client requested removal of decorative element restoration from scope

-$12,000-3d
Client Request

Jan 8, 2025

Rejected
CO-002
Foundation repair - north corner

Repair unexpected foundation damage discovered during brick removal

+$32,000+8d
Mike Chen

Dec 15, 2024

Approved
CO-001
Additional window restoration - east facade

Add restoration work for 6 windows on east facade discovered during inspection

+$18,500+5d
John Smith

Dec 5, 2024

Approved
Total Approved$50,500+13d

Budget Impact by Status

Approved$27,000
Pending$18,000

Change Order Distribution

2

Approved

2

Pending

0

Rejected

Fatal (S4)

0

Critical (S3)

1

Warning (S2)

0

Info (S1)

0

Unack'd

0

Impact

$6,500

S3Client

Client escalation: Quality concerns

Client has raised concerns about concrete finish quality in Section B. Site meeting requested for January 18. Prepare remediation options and timeline. Potential rework cost estimated at $6,500.

85

Attention

Impact: $6,500Due: Jan 18, 2025Created: Jan 13, 2025Ack'd by Lisa Wang

Alerts by Category

Financial

0

Schedule

0

Resource

0

Compliance

0

Client

1

$6,500

Pending

1

In Progress

1

Completed

2

Dismissed

0

Flags

1

Escalations

1

Updates

1

Comments

1

Activity Timeline

January 15, 2025(1 actions)
FlaggedUrgentPending

Flagged for CEO review due to budget overrun.

Sarah Johnsonproject: Heritage Building Restoration
09:30 AM
January 14, 2025(1 actions)
EscalatedHighIn Progress

Escalated to PM Lead for immediate review.

John SmithAssigned to: Sarah Johnsonalert: Budget Overrun - Labour Costs
02:15 PM
January 12, 2025(1 actions)
Update RequestedNormalCompleted

Requested update on north wall brick restoration timeline.

Sarah JohnsonAssigned to: Mike Chenproject: Heritage Building Restoration
11:00 AM
January 4, 2025(1 actions)
CommentLowCompleted

Weekly progress update: North wall restoration 75% complete.

John Smithproject: Heritage Building Restoration
05:00 PM

Action Distribution

Flagged1
Update Requested1
Comment1
Escalated1